When do you update the project management plan? Response:
A. Only at the beginning of the project B. Once in each project phase at the phase kick off C. After project closing to reflect lessons learned D. After an agreed upon change to areas covered by the plan
Answer: B
Question: 2
What kind of communication is addressed in the Communication Plan in ASAP? Please choose the correct answer. Response:
A. Communication to management and steering committee only B. Communication to project team members only C. External communication to project stakeholders only D. External and internal project communication
Answer: D
Question: 3
Which of the following must be included in the project charter? Please choose the correct answer. Response:
A. Project organizational chart B. Project objectives and benefits C. Project team training plan D. Solution architecture diagram
Answer: B
Question: 4
Which of the following tasks need to be completed successfully to complete the production cutover deliverable? There are 3 correct answers to this question. Response:
A. Obtain Production Data Sign-off B. Finalize Cutover plan C. Conduct Project Management Review Service D. Execute Multiple cutover Simulations E. Preform people readiness assessment
Answer: BDE
Question: 5
Which Accelerators from the ASAP Roadmap do you leverage to complete the Phase Closure and Sign-off Phase Deliverables? There are 2 correct answers to this question. Response:
A. Project Quality Gate Scorecard Template B. Project Setup Check list Sample C. Phase Closure Report Template D. On-Boarding Template
Answer: AC
Question: 6
In the Project Preparation phase Data Quality Analysis in initiated. Which Accelerators in the Data Migration Approach and Strategy deliverable is used to capture the baseline for Data Quality? Response:
A. Data Migration Workshop Findings Template B. Data Migration Approach and Strategy Template C. Data Audit Results Report Template D. Data Migration Scoping Questionnaire Template
Answer: C
Question: 7
Which SAP enabling tool can you use to evaluate the solution options and to define the solution scope? Please choose the correct answer. Response:
A. SAP Solution Composer B. SAP Project Composer C. SAP Solution Directory D. SAP Solution Documentation Assistant
Answer: A
Question: 8
Which of the following are characteristics of IT governance in the context of ASAP methodology? There are 3 correct answers to this question. Response:
A. IT governance is planned Michael Badgley Black Jersey , defined, and set up during the implementation project. B. IT governance is optimized during the Operate phase. C. IT governance is set up right after production cutover in the earl}.r stages of the Operate phase. D. IT governance is defined and completer put in place in the Project Preparation phase Denzel Perryman Black Jersey , as part of the project standards. E. IT governance is covered by ASAP methodology.
Answer: ADE
Question: 9
Which of the following are tasks of the Technical Operations and Handover Plan deliverable in the Realization phase? There are 3 correct answers to this question. Response:
A. Establish support processes- B. Conduct Technical Integration Check service. C. Execute performance tests. D. Validate support center (help desk) staffing strategy E. Set up business process monitoring.
Answer: ADE
Question: 10
Besides the request of instant value, customers need an early confirmation that requirements will be met. Which acceleration techniques in ASAP help provides an early confirmation? There are 2 correct answers to this question. Response:
A. Iterative build cycle B. Solution demo approach for blueprinting C. Sustainability management D. Service optimization
Answer: AB
Total Views: 95Word Count: 555See All articles From Author Larry Taggart Submitted 2018-04-15 20:01:42 An important fact that you need to keep in mind is that content Dan Feeney Black Jersey , brand awareness and user experience are all connected. This is something that DoDots Tony Medrano had in mind when wanting to promote the technology that allowed Dots from the DoDots Tony Medrano program to be sent to pre-screened users. There is so much that can be done when you have access to a small bit of content rather than an entire web page, where the user journey can be harder to redirect.
If you were to compare the needs of people from two decades ago to the ones of today鈥檚 web users Mike Williams Black Jersey , the differences are not that big. Of course, most individuals have become rather impatient and are used to finding the bit of information they need in a matter of seconds. But Kyzir White Black Jersey , when it comes to impulsive reactions, one would have been more likely to buy a product if a notification would have been received on their phone many years ago or yesterday.